How do you correctly fill cables into a cable carrier?

Short answerLay cables into the chain free of tension while it rests in the neutral, extended position, and only then fix them with strain relief at both the fixed point and the driver. Each cable belongs in its own compartment, with 10 to 20% clearance and without twisting around each other. Never fix inside the bend: only at the two ends.

6 min readUpdated

trekontlasting ≤ 100 mmtrekontlastingmeetpunt Ø
Figure: Strain relief at fixed point and driver, cable free of tension in the bend.

How do you prepare the cables?

Unwind cables from the reel, never loop them off the coil: that introduces torsion which later shows up as corkscrewing. Let cables lie extended for at least an hour, longer in cold weather, so the sheath relaxes. Then re-measure diameters and check for transport damage.

What is the neutral position?

Lay the chain out straight on the floor or in the trough, with the bend flat. In that position every cable sits at its natural length. If you fill it while bent, the cable turns out too short or too long at the opposite position and pulls at the end connectors.

Where and how do you fit strain relief?

At both ends, within 100 mm of the end connector, with a clamp gripping the sheath over its full circumference. Do not use a cable tie directly on the sheath of moving cables: a tie cuts in. On vertical arrangements, add relief every two metres.

What do you check on the first test run?

First move the axis by hand or at low speed across the full travel. Watch the bend: does it roll evenly, or does a cable pull the compartments askew? After ten strokes, feel the cables at the end connector; heat or tension there means the cable was laid in too short. Repeat the check after 100 and after 5000 strokes.

Table — Installation sequence and checkpoints
StepActionCheckTime
1Ketting uitgestrekt leggenBocht vlak5 min
2Vakindeling zettenVulling ≤ 60%10 min
3Kabels afrollen en laten rustenGeen torsie60 min
4Kabels invullenSpeling 10–20%20 min
5Trekontlasting monteren≤ 100 mm van eind15 min
6Stegen sluitenVolledig vergrendeld10 min
7ProefritBocht rolt gelijkmatig10 min

Frequently asked questions

May cables inside the chain be extended with a joint?
No, never inside the moving section. A joint is stiffer than the cable and forms a break point. Extend only outside the chain, behind the strain relief.
How do you stop cables twisting around each other?
One cable per compartment, and mark a line on the sheath every metre while filling. If the marks stay aligned, there is no torsion.
Can Wisman Group supply the chain pre-filled?
Yes, we supply chains complete with cables, hoses, strain relief and end connectors, assembled to length. Request it through the quote form; you also receive the assembly drawing.